The Challenges

Owner’s project manager for the Town of Norton for this MSBA-funded 150,000 SF renovation and a 20,000 SF addition containing new science classrooms, auditorium, library, cafeteria, expanded common space, and entrance lobby. The project included a two-floor addition on the east end of the school, along with a complete repair/renovation of the existing building. The renovation brought the building up to code and now meets all state space and educational requirements. The school was fully occupied during the two-year construction period. Anser developed a complex phased construction schedule to allow students daily and safe access to necessary facilities. Bringing the construction manager on board early in the design phase of this multi-year project enabled the complex phasing and scheduling to be pro-actively planned. The project was performed under the Construction Manage at Risk (CMaR, Chap 149a) delivery method.