Project Info

Fay School
Fay School Campus Master Plan + Projects
Owner Project Management
Southborough, MA

 

The Challenges

36,000 SF Primary school, two dormitories , 20,000 gal. wastewater treatment plant, health center, track and field, swimming pool and bathhouse.

As OPM, we led the team through the entire design process, facilitating decision-making for the implementation of the $41 million campus master plan that consisted of a new 36,000 SF primary school, two new dormitories, a 20,000-gallon per day wastewater treatment facility, maintenance building, renovation of an existing dormitory to serve as a health center for students, and a remote 30-acre track and field project. We led the team through the entire design process and construction process, facilitating decision-making to ensure programmatic and budgetary goals were met.