Project Info

Edward W. Brooke Charter School
Edward W. Brooke Charter School, Mattapan
Owner Project Management
Mattapan, MA

 

The Challenges

Owner’s project manager for the new site of this expanding K-8 Charter School. The project included a 57,000 SF renovation, 2,500 SF addition and full site development. Anser also completed a notice of project change (NPC) within the Article 80 process. The project was on an accelerated schedule and was completed in time for the 2014-15 school year; both new construction and renovation were performed under the Construction Manager at Risk (CMaR/Chapter 149A procurement method.