Project Info

Southern California Edison (SCE)
Camp Edison Administration Building
Project Management, Construction Management, Project Controls
Shaver Lake, California

The Challenges

Anser provided project management, construction management and project controls to assist Southern California Edison with the remodel and construction expansion of the existing Camp Edison Administration Building with site improvements. Building occupancy limit of 23 was insufficient for peak staffing needs of 35 office staff and 40 field staff. Fire alarm and fire suppression systems were installed as well as installation of energy efficient LED lighting as is standard on SCE projects. Site improvements included pavement renovation for emergency vehicles and staff parking, demolition of the existing temporary trailer, and improved ADA compliance, as necessary.

Camp Edison Administration Building